# Construction: a Monday WIP review from job-cost exports, with permits, price indexes and weather beside your jobs

The work-in-progress schedule says which jobs are over-billed, under-billed or heading for a loss. Here's how to build it from the job-cost export you already have, and what public data adds to the Monday conversation.

Storek teamDecember 16, 20254 min read

![Funnel of 24 active construction jobs narrowing to 9 under-billed, 4 more than 10% under and 2 projecting a loss, with the under-billed stage opened into a table of jobs, percent complete, percent billed and the gap.](https://storek.io/blog/construction-wip-review-job-cost/hero.webp)

Sample dataA weekly WIP review drilled from all jobs to the ones to act on. Illustrative data.

On this page

1.  [The WIP math in four lines](#the-wip-math-in-four-lines)
2.  [Building it from the export](#building-it-from-the-export)
3.  [Context from public data](#context-from-public-data)
4.  [Crew data stays sealed](#crew-data-stays-sealed)

Monday morning, the controller and the project managers go through the work-in-progress schedule. Which jobs are behind on billing? Which are ahead? Is anything quietly turning into a loss? The answers come from the job-cost system, usually as an export that someone reshapes in a spreadsheet every week.

The math is not hard. The weekly rebuild is the part that eats the morning, and the part where mistakes slip in. This walkthrough uses an invented commercial contractor with six active jobs.

## The WIP math in four lines

Most contractors use the cost-to-cost method for this:

1.  **Percent complete** = cost to date ÷ estimated total cost
2.  **Earned revenue** = percent complete × contract value
3.  **Over/(under) billed** = billed to date − earned revenue
4.  **Projected margin** = contract value − estimated total cost

Here are the six jobs, in thousands of dollars:

Job

Contract

Est. total cost

Cost to date

% complete

Earned

Billed

Over/(under)

Elm St Medical

12,400

11,160

6,250

56.0%

6,944

7,158

214

Harbor Logistics

9,800

10,050

7,120

70.8%

6,943

6,555

(388)

Westview School

8,600

7,740

2,180

28.2%

2,422

2,518

96

Pine Ridge Apts

7,900

8,120

3,410

42.0%

3,318

3,067

(251)

Civic Garage

5,300

4,720

3,950

83.7%

4,435

4,292

(143)

Mercer Retail

4,200

3,760

1,140

30.3%

1,273

1,133

(140)

Sample dataSix active jobs in $ thousands. Highlighted: the two jobs whose estimated cost is above the contract value. Net position: $612,000 under-billed. Invented data.

Three things jump out. Harbor Logistics and Pine Ridge Apartments are estimated to cost more than their contracts, so they’re projecting a loss. Both are also under-billed, which makes the cash position worse. And Civic Garage is 84% done but under-billed by $143,000, which usually means a pay application is late. (Your accountant will treat loss jobs differently when the books are closed; this review only flags them.)

## Building it from the export

1.  ### Drop off the job-cost and billing exports

    Upload the export as it comes out of the job-cost system: CSV or Excel, with each sheet becoming its own table. Storek checks the row count of every load against the source and fails loudly on a mismatch, so a short file doesn’t become a short WIP.

2.  ### Ask the Monday questions

    “Where are we under-billed on WIP this month?” “Which active jobs are trending over budget?” Each answer shows the SQL that ran, so the controller can check that percent complete was calculated cost-to-cost and not from a PM’s estimate field.

3.  ### Pin the schedule and the tiles

    Pin the answers into a dashboard: contract value, net over/(under) billing, jobs projecting a loss, and the billing position by job. Next Monday, the new export lands and every tile re-runs its checked query.

4.  ### Work the exceptions as a review table

    Put the jobs that need action into a table with a review workflow (Open, Accepted, In progress, Done), add a column for the PM’s note, and work through it in the meeting. Approved rows can be published as their own dataset for follow-up.

5.  ### Send the summary

    For the owner, a lender or the bonding company, export a branded PDF report with an executive summary, the findings and an appendix that lists every query and row count.

## Context from public data

Your own jobs explain most of the WIP. Public data explains some of the rest. Storek’s catalog includes one-click public datasets such as building permits, a construction price index and weather, which can sit beside your job data in the same workspace.

**Material prices.** If Pine Ridge’s estimate was built when lumber was cheaper, a rising index explains part of its overrun and tells you which other estimates to revisit.

![Line chart of a monthly material price index, November to October, with November set to 100: lumber rises to about 111 in April and ends near 108; ready-mix concrete climbs slowly to about 106.](https://storek.io/blog/construction-wip-review-job-cost/price-index.webp)

Sample dataA material price index beside your jobs, rebased to November = 100. The shape of this chart is invented; the real one comes from a public price index dataset.

**Weather.** “Do rain days explain our slipped concrete pours?” is a question the construction team can now ask directly, by joining weather to job sites by place and week.

![Dark-mode heatmap of rain days by job site and week from September 1 to October 20; the weeks of October 6 and 13 are darkest across most sites.](https://storek.io/blog/construction-wip-review-job-cost/rain-days.webp)

Sample dataRain days by job site and week. Two wet weeks in October line up with the slipped pours. Invented data.

**Permits.** Permit volumes in your area show where the next bids are coming from, a different conversation from WIP but often the same meeting.

## Crew data stays sealed

Job files carry personal data: crew phone numbers, owner contacts, subcontractor tax IDs, Social Security numbers on certified payroll. Storek finds them when data lands and masks them whenever anyone reads it. An SSN reads `***-**-6789`, and tokenized worker IDs still join payroll to timecards, so labor cost by job stays correct without anyone seeing who’s who.

About the examples

The company, people and figures in this article are illustrative.

OperationsMetric definitions

## Keep reading

[Solutions · Construction & field operations**Know which jobs are over budget — and why.**Open the page →](https://storek.io/solutions/construction)[Platform how-to**Make Sense of Very Wide Exports Without the Grind**Read the article →](https://storek.io/blog/wide-export-lookup-table-unpivot)[Platform how-to**From Scattered Spreadsheets to One Picture**Read the article →](https://storek.io/blog/scattered-spreadsheets-to-one-picture)

FAQ

## Questions, answered.

What is a WIP report in construction?

A work-in-progress schedule lists each active job with its contract value, estimated total cost, cost to date, percent complete, revenue earned so far and amount billed. The difference between billed and earned shows whether each job is over-billed or under-billed.

How do you calculate over and under billing?

With the cost-to-cost method: percent complete is cost to date divided by estimated total cost; earned revenue is percent complete times the contract value; over or under billing is billed to date minus earned revenue. A positive result is over-billing, a negative one under-billing.

What does under-billing mean?

You've done more work than you've invoiced. It can mean a missed billing, a pay application held up by the owner, or costs running ahead of the estimate. Each needs a different fix, which is why the Monday review asks why, job by job.

Can Storek pull our job-cost data automatically?

Most construction teams upload the job-cost and billing exports (CSV or Excel) each week; dashboards follow the newest version. Public data such as building permits, price indexes and weather can be added in one click.

Book a demo

## See your own data, delivered.

30 minutes. Your data or our sample. No slide deck. Pick a time straight after the form.